BetaActiveWindAECLBNL
18 MW generation in Gentry, MO · In queue since April 2017
18 MW
Capacity
1
Components
Wind
8y 11m
In Queue
IA Executed
IA Status
Interconnection Timeline
Total Duration
8y 11m
Construction75%
Queue EntryApr 4, 2017
Interconnection request submitted to ISO/RTO
Interconnection Study
Project undergoes interconnection studies to assess grid impact.
Typical: 18–36 months
Interconnection Agreement
Interconnection agreement executed — binding commitment to build
Typical: 30–60 days (negotiation)
ConstructionCurrent
Project under construction
Typical: 18–36 months
Commercial Operation
Commercial operation date not yet determined
Project Details
State
MO
County
Gentry
Region
Southeast
Developer
—
Utility
Associated Electric Cooperative, Incorporated
Entity
AEC
Point of Interconnection
Winslow 161 kV Substation
Data Source
LBNL