— Project Summary

Queue ID
AEC-GI-53
Capacity
238 MW
Technology
Wind
Status
active
Location
Nodaway, MO
Region
Southeast
Developer
IA Status
IA Executed

BetaActiveWindAECLBNL

238 MW generation in Nodaway, MO · In queue since May 2016 · Proposed COD December 2018

238 MW

Capacity

1

Components

Wind

9y 10m

In Queue

IA Executed

IA Status

COD target: 2018

Interconnection Timeline

Total Duration

2y 7m

Schedule

89 months past proposed COD

Construction75%
Queue EntryMay 2, 2016

Interconnection request submitted to ISO/RTO

Interconnection Study

Project undergoes interconnection studies to assess grid impact.

Typical: 18–36 months

Interconnection Agreement

Interconnection agreement executed — binding commitment to build

Typical: 30–60 days (negotiation)

ConstructionCurrent

Project under construction

Typical: 18–36 months

Commercial Operation

Proposed COD: 2018-12-01

Project Details

State

MO

County

Nodaway

Region

Southeast

Developer

Utility

Associated Electric Cooperative, Incorporated

Entity

AEC

Point of Interconnection

Maryville 161 kV

Data Source

LBNL

No news available for this project.