238 MW generation in Nodaway, MO · In queue since May 2016 · Proposed COD December 2018
238 MW
Capacity
1
Components
Wind
9y 10m
In Queue
IA Executed
IA Status
COD target: 2018
Interconnection Timeline
Total Duration
2y 7m
Schedule
89 months past proposed COD
Construction75%
Queue EntryMay 2, 2016
Interconnection request submitted to ISO/RTO
Interconnection Study
Project undergoes interconnection studies to assess grid impact.
Typical: 18–36 months
Interconnection Agreement
Interconnection agreement executed — binding commitment to build
Typical: 30–60 days (negotiation)
ConstructionCurrent
Project under construction
Typical: 18–36 months
Commercial Operation
Proposed COD: 2018-12-01
Project Details
State
MO
County
Nodaway
Region
Southeast
Developer
—
Utility
Associated Electric Cooperative, Incorporated
Entity
AEC
Point of Interconnection
Maryville 161 kV
Data Source
LBNL