BetaActiveCoalAECLBNL
1.7 MW generation in Randolph, MO · In queue since November 2009 · Proposed COD May 2010
1.7 MW
Capacity
1
Components
Coal
16y 4m
In Queue
In Progress (unknown study)
IA Status
COD target: 2010
Interconnection Timeline
Total Duration
6 months
Schedule
194 months past proposed COD
In Study38%
Queue EntryNov 4, 2009
Interconnection request submitted to ISO/RTO
Interconnection StudyCurrent
Project undergoes interconnection studies to assess grid impact.
Typical: 18–36 months
Interconnection Agreement
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Commercial Operation
Proposed COD: 2010-05-01
Project Details
State
MO
County
Randolph
Region
Southeast
Developer
—
Utility
Associated Electric Cooperative, Incorporated
Entity
AEC
Point of Interconnection
TH Switchyard (161 kV Bus)
Data Source
LBNL
No news available for this project.