BetaActiveCoalAECLBNL
20 MW generation in New Madrid, MO · In queue since October 2009 · Proposed COD November 2011
20 MW
Capacity
1
Components
Coal
16y 5m
In Queue
In Progress (unknown study)
IA Status
COD target: 2011
Interconnection Timeline
Total Duration
2y 1m
Schedule
175 months past proposed COD
In Study38%
Queue EntryOct 24, 2009
Interconnection request submitted to ISO/RTO
Interconnection StudyCurrent
Project undergoes interconnection studies to assess grid impact.
Typical: 18–36 months
Interconnection Agreement
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Commercial Operation
Proposed COD: 2011-11-01
Project Details
State
MO
County
New Madrid
Region
Southeast
Developer
—
Utility
Associated Electric Cooperative, Incorporated
Entity
AEC
Point of Interconnection
NM Switchyard (345 kV Bus)
Data Source
LBNL
No news available for this project.