BetaActiveSolarAECLBNL
200 MW generation in Vernon, MO · In queue since December 2024 · Proposed COD December 2028
200 MW
Capacity
1
Components
Solar
1y 3m
In Queue
System Impact Study
IA Status
COD target: 2028
Interconnection Timeline
Total Duration
4 years
Impact Study25%
Queue EntryDec 9, 2024
Interconnection request submitted to ISO/RTO
Interconnection StudyCurrent
Project undergoes interconnection studies to assess grid impact.
Typical: 18–36 months
Interconnection Agreement
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Commercial Operation
Proposed COD: 2028-12-31
Project Details
State
MO
County
Vernon
Region
Southeast
Developer
—
Utility
Associated Electric Cooperative, Incorporated
Entity
AEC
Point of Interconnection
Camp Clark 161 kV
Data Source
LBNL
No news available for this project.