BetaActiveWindAECLBNL
300 MW generation in Craig, OK · In queue since September 2024 · Proposed COD December 2027
300 MW
Capacity
1
Components
Wind
1y 6m
In Queue
System Impact Study
IA Status
COD target: 2027
Interconnection Timeline
Total Duration
3y 3m
Impact Study25%
Queue EntrySep 3, 2024
Interconnection request submitted to ISO/RTO
Interconnection StudyCurrent
Project undergoes interconnection studies to assess grid impact.
Typical: 18–36 months
Interconnection Agreement
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Commercial Operation
Proposed COD: 2027-12-31
Project Details
State
OK
County
Craig
Region
Southeast
Developer
—
Utility
Associated Electric Cooperative, Incorporated
Entity
AEC
Point of Interconnection
Sportsman-Blackberry 345 kV line
Data Source
LBNL
No news available for this project.