— Project Summary

Queue ID
AEC-GI-123
Capacity
300 MW
Technology
Wind
Status
active
Location
Craig, OK
Region
Southeast
Developer
IA Status
System Impact Study

BetaActiveWindAECLBNL

300 MW generation in Craig, OK · In queue since September 2024 · Proposed COD December 2027

300 MW

Capacity

1

Components

Wind

1y 6m

In Queue

System Impact Study

IA Status

COD target: 2027

Interconnection Timeline

Total Duration

3y 3m

Impact Study25%
Queue EntrySep 3, 2024

Interconnection request submitted to ISO/RTO

Interconnection StudyCurrent

Project undergoes interconnection studies to assess grid impact.

Typical: 18–36 months

Interconnection Agreement

Interconnection agreement not yet executed

Typical: 30–60 days (negotiation)

Commercial Operation

Proposed COD: 2027-12-31

Project Details

State

OK

County

Craig

Region

Southeast

Developer

Utility

Associated Electric Cooperative, Incorporated

Entity

AEC

Point of Interconnection

Sportsman-Blackberry 345 kV line

Data Source

LBNL