BetaActiveWindAECLBNL
500 MW generation in Randolph, MO · In queue since May 2024 · Proposed COD December 2028
500 MW
Capacity
1
Components
Wind
1y 10m
In Queue
Facility Study
IA Status
COD target: 2028
Interconnection Timeline
Total Duration
4y 7m
Facilities Study50%
Queue EntryMay 20, 2024
Interconnection request submitted to ISO/RTO
Interconnection StudyCurrent
Project undergoes interconnection studies to assess grid impact.
Typical: 18–36 months
Interconnection Agreement
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Commercial Operation
Proposed COD: 2028-12-31
Project Details
State
MO
County
Randolph
Region
Southeast
Developer
—
Utility
Associated Electric Cooperative, Incorporated
Entity
AEC
Point of Interconnection
McCredie 345 kV
Data Source
LBNL
No news available for this project.