245 MW generation in Randolph, MO · In queue since April 2024 · Proposed COD February 2029
245 MW
Capacity
1
Components
Solar
1y 11m
In Queue
Facility Study
IA Status
COD target: 2029
Interconnection Timeline
Total Duration
4y 10m
Facilities Study50%
Queue EntryApr 29, 2024
Interconnection request submitted to ISO/RTO
Interconnection StudyCurrent
Project undergoes interconnection studies to assess grid impact.
Typical: 18–36 months
Interconnection Agreement
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Commercial Operation
Proposed COD: 2029-02-15
Project Details
State
MO
County
Randolph
Region
Southeast
Developer
—
Utility
Associated Electric Cooperative, Incorporated
Entity
AEC
Point of Interconnection
Thomas Hill 345 kV
Data Source
LBNL
No news available for this project.