BetaActiveSolarAECLBNL
32 MW generation in Mississippi, MO · In queue since July 2023 · Proposed COD March 2026
32 MW
Capacity
1
Components
Solar
2y 8m
In Queue
Facility Study
IA Status
COD target: 2026
Interconnection Timeline
Total Duration
2y 8m
Facilities Study50%
Queue EntryJul 18, 2023
Interconnection request submitted to ISO/RTO
Interconnection StudyCurrent
Project undergoes interconnection studies to assess grid impact.
Typical: 18–36 months
Interconnection Agreement
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Commercial Operation
Proposed COD: 2026-03-31
Project Details
State
MO
County
Mississippi
Region
Southeast
Developer
—
Utility
Associated Electric Cooperative, Incorporated
Entity
AEC
Point of Interconnection
Anniston - Wyatt 69 kV
Data Source
LBNL
No news available for this project.