46 MW generation in New Madrid, MO · In queue since May 2023 · Proposed COD October 2024
46 MW
Capacity
1
Components
Gas
2y 10m
In Queue
IA Executed
IA Status
COD target: 2024
Interconnection Timeline
Total Duration
1y 5m
Schedule
18 months past proposed COD
Construction75%
Queue EntryMay 3, 2023
Interconnection request submitted to ISO/RTO
Interconnection Study
Project undergoes interconnection studies to assess grid impact.
Typical: 18–36 months
Interconnection Agreement
Interconnection agreement executed — binding commitment to build
Typical: 30–60 days (negotiation)
ConstructionCurrent
Project under construction
Typical: 24–48 months
Commercial Operation
Proposed COD: 2024-10-01
Project Details
State
MO
County
New Madrid
Region
Southeast
Developer
—
Utility
Associated Electric Cooperative, Incorporated
Entity
AEC
Point of Interconnection
St Francis 161 kV
Data Source
LBNL