BetaActiveGasAECLBNL
460 MW generation in Payne, OK · In queue since July 2022 · Proposed COD June 2026
460 MW
Capacity
1
Components
Gas
3y 8m
In Queue
IA Executed
IA Status
COD target: 2026
Interconnection Timeline
Total Duration
3y 11m
Construction75%
Queue EntryJul 21, 2022
Interconnection request submitted to ISO/RTO
Interconnection Study
Project undergoes interconnection studies to assess grid impact.
Typical: 18–36 months
Interconnection Agreement
Interconnection agreement executed — binding commitment to build
Typical: 30–60 days (negotiation)
ConstructionCurrent
Project under construction
Typical: 24–48 months
Commercial Operation
Proposed COD: 2026-06-30
Project Details
State
OK
County
Payne
Region
Southeast
Developer
—
Utility
Associated Electric Cooperative, Incorporated
Entity
AEC
Point of Interconnection
Stillwater 138 kV Bus
Data Source
LBNL
No news available for this project.