381.6 MW Natural Gas operating in Jefferson, WI — Midcontinent Independent Transmission System Operator, Inc..
381.6 MW
Nameplate Capacity
4
Generators
units
Natural Gas Fired Combustion Turbine
Technology
1993
Operating Since
Coordinates
43.1669, -88.6900
County
Jefferson, WI
Nearby Plants
| Field | EIA | GEM | Wikidata |
|---|---|---|---|
| Operator | Wisconsin Electric Power Co | Wisconsin Electric Power | — |
| Owner(s) | Wisconsin Electric Power Co | WEC Energy Group | — |
| Status | Operating | — | — |
The Concord power plant, located in Jefferson County, Wisconsin, has a total capacity of 381.6 MW. The plant began operating in 1993 and is owned by WEC Energy Group, with Wisconsin Electric Power Co. listed as the EIA operator. Concord utilizes four natural gas-fired combustion turbine generators. It is connected to the Midcontinent Independent Transmission System Operator, Inc. (MISO) balancing authority and resides within the ReliabilityFirst Corporation (RFC) NERC region.
Concord's latest annual generation was 175,184 MWh, resulting in a capacity factor of 5.2%. The plant's installed cost was $334.09 per kW, according to FERC data. Concord is ranked as the 9th largest power plant out of 19 in Wisconsin, and 562nd out of 945 nationally.
Generated from EIA, GEM, and public data sources
NERC Region
RFC
Balancing Authority
Midcontinent Independent Transmission System Operator, Inc..
Grid Voltage
138 kV
Regulatory Status
RE
Entity Type
Investor-Owned Utility
Sector
Electric Utility
2.2K MWh
Latest Month
175.2K MWh
Annual Generation
5.2%
Capacity Factor
$372/kW
Installed Cost
$46.0/MWh
Operating Cost
Wisconsin Electric Power Company
Reporting Utility
Annual Capital & Operating Expenses
Cumulative Installed Cost
Per-Unit Cost Trends
Market Position
ISO/RTO Market
MISO
LMP Node
WEC.CCDGTC1
Pricing Hub
MICHIGAN.HUB
Location Type
Generation Node
Node Source
EIA-860 direct report
Bridge Data Centres Plans Major Investment with Global Partners to Strengthen Singapore’s Position as Asia Pacific’s Leading AI Hub
Strategic Investment of S$3-5 billion in Singapore to advance AI-ready data centre developments, supporting over 2 GW of AI-ready capacity.
This data center proposal gave Michigan cities a 48-hour deadline
On Jan. 16, a prospective developer fired off an email to government and economic development leaders in nine cities across Michigan,...
Brochu Nurseries To Install Community Solar Project On Lower-Value, Degraded Farmland
The project is expected to fund electrical grid improvements and generate more than $1 million in new tax revenue for the city of Concord.