5 MW Solar operating in Pulaski, AR — Southwest Power Pool
5 MW
Nameplate Capacity
1
Generators
unit
Solar Photovoltaic
Technology
2024
Operating Since
Coordinates
34.7435, -92.1799
County
Pulaski, AR
Nearby Plants
| Field | EIA | GEM | Wikidata |
|---|---|---|---|
| Operator | Today's Power, Inc. | Today's Power, Inc. | — |
| Owner(s) | Today's Power, Inc. | Today's Power, Inc. | — |
| Status | Operating | operating | — |
GEM identifies the owner as Today's Power, Inc.
This entity is not yet in the GEM ownership database — chain unavailable.
NLRED 5MW is a solar photovoltaic power plant located in Pulaski County, Arkansas. The plant has a total capacity of 5 MW and began operating in 2024. It is owned and operated by Today's Power, Inc. The facility consists of a single generator and utilizes single-axis solar tracking technology to maximize energy capture.
The plant's primary fuel source is solar energy. In its most recent year of operation, NLRED 5MW generated 2,882 MWh of electricity, resulting in a capacity factor of 6.6%. The plant operates within the Southwest Power Pool (SPP) balancing authority and the SERC NERC region. NLRED 5MW is ranked as the 25th largest solar plant in Arkansas out of 77, and nationally it is ranked 2561 out of 7108.
Generated from EIA, GEM, and public data sources
NERC Region
SERC
Balancing Authority
Southwest Power Pool
Grid Voltage
13.2 kV
Regulatory Status
RE
Entity Type
Cooperative
Sector
Electric Utility
500 MWh
Latest Month
2.9K MWh
Annual Generation
6.6%
Capacity Factor
No financial data available for this plant.
Point of Interconnection
Nearest Substation
Faulkner Lake Substation · 115 kV
Substation Distance
< 10 km
Operator
Entergy Arkansas
Coord Source
OSM spatial
Market Position
ISO/RTO Market
SPP
LMP Node
—
Pricing Hub
SPP South Hub
Node Source
OSM spatial match
Substation identified. Node ID not yet resolved against ISO roster.