3.3 MW Solar operating in Weld, CO — Public Service Company of Colorado
3.3 MW
Nameplate Capacity
1
Generators
unit
Solar Photovoltaic
Technology
2024
Operating Since
Coordinates
40.4810, -104.7159
County
Weld, CO
Nearby Plants
| Field | EIA | GEM | Wikidata |
|---|---|---|---|
| Operator | Green Street Power Partners | Green Street Power Partners | — |
| Owner(s) | Green Street Power Partners | Green Street Power Partners | — |
| Status | Operating | operating | — |
GEM identifies the owner as Green Street Power Partners
This entity is not yet in the GEM ownership database — chain unavailable.
ECA CO Greeley is a solar photovoltaic power plant located in Weld County, Colorado. The facility has a total capacity of 3.3 MW and began operating in 2024. It is owned and operated by Green Street Power Partners. The plant utilizes a single-axis tracking system to maximize solar energy capture.
The plant consists of one generator and primarily uses solar energy as its fuel source. In its most recent year of operation, ECA CO Greeley generated 78 MWh of electricity, achieving a capacity factor of 0.3%. The plant operates within the Public Service Company of Colorado balancing authority and the Western Electricity Coordinating Council (WECC) NERC region. ECA CO Greeley ranks as the 71st largest power plant in Colorado out of 177, and nationally it ranks 3721 out of 7108.
Generated from EIA, GEM, and public data sources
NERC Region
WECC
Balancing Authority
Public Service Company of Colorado
Grid Voltage
12.47 kV
Regulatory Status
NR
Entity Type
Commercial
Sector
IPP Non-CHP
76 MWh
Latest Month
78 MWh
Annual Generation
0.3%
Capacity Factor
No financial data available for this plant.