1.4 MW Batteries (1 MW) + Solar Photovoltaic (1 MW) under construction in Los Angeles, CA — California Independent System Operator
1.4 MW
Nameplate Capacity
2
Generators
units
Hybrid (2)
Technology
Batteries + Solar Photovoltaic
—
Operating Since
Coordinates
34.1265, -118.6981
County
Los Angeles, CA
Nearby Plants
| Field | EIA | GEM | Wikidata |
|---|---|---|---|
| Operator | Las Virgenes Road Solar Project 2022, LLC | Greenbacker Renewable Energy | — |
| Owner(s) | Las Virgenes Road Solar Project 2022, LLC | — | — |
| Status | Under construction | operating | — |
The Las Virgenes MWD - Composting Plant, located in Los Angeles County, California, is a hybrid power plant with a total capacity of 1.4 MW. The plant is owned and operated by Las Virgenes Road Solar Project 2022, LLC. It utilizes both solar photovoltaic technology and batteries for energy storage. The facility consists of two generators and employs a fixed tilt solar tracking system. Its primary fuel source is listed as MWH.
The plant operates within the California Independent System Operator (CAISO) balancing authority and the Western Electricity Coordinating Council (WECC) NERC region. In terms of size, the Las Virgenes MWD - Composting Plant is ranked 288th out of 300 power plants in California and 1173rd out of 1205 plants nationally.
Generated from EIA, GEM, and public data sources
NERC Region
WECC
Balancing Authority
California Independent System Operator
Grid Voltage
16.5 kV
Regulatory Status
NR
Entity Type
Independent Power Producer
Sector
IPP Non-CHP
No generation data available for this plant.
No financial data available for this plant.
Market Position
ISO/RTO Market
CAISO
LMP Node
MOORPARK_6_GN010
Pricing Hub
TH_SP15_GEN-APND
Location Type
Pricing Node
Node Source
Curated node match