6 MW Solar operating in Langlade, WI — Midcontinent Independent Transmission System Operator, Inc..
6 MW
Nameplate Capacity
1
Generators
unit
Solar Photovoltaic
Technology
2024
Operating Since
Coordinates
45.1239, -89.1754
County
Langlade, WI
Owner data does not fully agree across sources.
EIA typically reports the operating utility, while GEM resolves to the financial owner or parent corporation. Both can be correct.
| Field | EIA | GEM | Wikidata |
|---|---|---|---|
| Operator | Wisconsin Public Service Corp | Madison Gas & Electric Co | — |
| Owner(s) | Wisconsin Public Service Corp | MGE Energy | — |
| Status | Operating | operating | — |
The Antigo-Forrest Street Solar Project is a 6 MW solar photovoltaic power plant located in Langlade County, Wisconsin. The plant began operating in 2024 and has a single generator. It is owned by MGE Energy and operated by Wisconsin Public Service Corp. The facility utilizes single-axis tracking for its solar panels.
In its most recent year of operation, the plant generated 279 MWh of electricity, resulting in a capacity factor of 0.5%. The plant operates within the Midcontinent Independent Transmission System Operator (MISO) balancing authority and the RFC NERC region. The installed cost of the facility was $1531.79 per kW, according to FERC data. The Antigo-Forrest Street Solar Project is ranked as the 36th largest solar plant in Wisconsin out of 99, and 2121st nationally out of 7108.
Generated from EIA, GEM, and public data sources
NERC Region
RFC
Balancing Authority
Midcontinent Independent Transmission System Operator, Inc..
Grid Voltage
24.9 kV
Regulatory Status
RE
Entity Type
Investor-Owned Utility
Sector
Electric Utility
225 MWh
Latest Month
279 MWh
Annual Generation
0.5%
Capacity Factor
$1,532/kW
Installed Cost
Wisconsin Public Service Corporation
Reporting Utility
Point of Interconnection
Nearest Substation
Aurora St · 115 kV
Substation Distance
< 10 km
Coord Source
OSM spatial
Market Position
ISO/RTO Market
MISO
LMP Node
—
Pricing Hub
MICHIGAN.HUB
Node Source
OSM spatial match
Substation identified. Node ID not yet resolved against ISO roster.