7.3 MW Batteries (2 MW) + Solar Photovoltaic (5 MW) operating in Plymouth, MA — ISO New England Inc.
7.3 MW
Nameplate Capacity
2
Generators
units
Hybrid (2)
Technology
Batteries + Solar Photovoltaic
2025
Operating Since
Coordinates
41.9641, -70.7888
County
Plymouth, MA
Nearby Plants
| Field | EIA | GEM | Wikidata |
|---|---|---|---|
| Operator | Greenbacker Renewable Energy Corporation | Greenbacker Renewable Energy Corp | — |
| Owner(s) | Greenbacker Renewable Energy Corporation | Greenbacker Renewable Energy Corp | — |
| Status | Operating | operating | — |
GEM identifies the owner as Greenbacker Renewable Energy Corp
This entity is not yet in the GEM ownership database — chain unavailable.
Upland is a hybrid power plant located in Plymouth County, Massachusetts. The facility, owned and operated by Greenbacker Renewable Energy Corporation, commenced operations in 2025. It combines solar photovoltaic generation with battery energy storage, utilizing two generators to achieve a total capacity of 7.3 MW. The primary fuel type is listed as MWH, reflecting the energy storage component. The solar array employs a fixed tilt tracking system. The battery energy storage system (BESS) has a duration of 2.35 hours.
Upland operates within the ISO New England Inc. balancing authority and the NPCC NERC region. As of the latest rankings, the plant is the 45th largest in Massachusetts out of 126 facilities and ranks 907th nationally out of 1205.
Generated from EIA, GEM, and public data sources
NERC Region
NPCC
Balancing Authority
ISO New England Inc.
Grid Voltage
22.8 kV
Regulatory Status
NR
Entity Type
Independent Power Producer
Sector
IPP Non-CHP
No generation data available for this plant.
No financial data available for this plant.
Point of Interconnection
Nearest Substation
Brook Street Substation · 115 kV
Substation Distance
1.825 km
Operator
Eversource
Coord Source
OSM spatial
Market Position
ISO/RTO Market
ISO-NE
LMP Node
LD.BROOK_ST23
Pricing Hub
.H.INTERNAL_HUB
Node Source
Curated node match