1306 MW Natural Gas under construction in Orange, TX — Midcontinent Independent Transmission System Operator, Inc..
1,306 MW
Nameplate Capacity
3
Generators
units
Natural Gas Fired Combined Cycle
Technology
—
Operating Since
Coordinates
30.0253, -93.8713
County
Orange, TX
Nearby Plants
| Field | EIA | GEM | Wikidata |
|---|---|---|---|
| Operator | Entergy Texas Inc. | Entergy Texas | — |
| Owner(s) | Entergy Texas Inc. | Entergy | — |
| Status | Under construction | — | — |
The Orange County Advanced Power Station is a 1306 MW natural gas-fired combined cycle power plant located in Orange County, Texas. The plant is owned by Entergy and operated by Entergy Texas Inc. It consists of 3 generators utilizing natural gas as its primary fuel source. The plant ranks as the 9th largest in Texas out of 144 power plants, and 86th nationally out of 945 plants.
The power station operates within the Midcontinent Independent Transmission System Operator (MISO) balancing authority and the SERC NERC region. Public reporting indicates 10 news articles related to the plant, with 5 focused on regulatory matters, 3 on industry news, and 2 covering grid-related topics.
Generated from EIA, GEM, and public data sources
NERC Region
SERC
Balancing Authority
Midcontinent Independent Transmission System Operator, Inc..
Grid Voltage
138 kV
Regulatory Status
RE
Entity Type
Investor-Owned Utility
Sector
Electric Utility
No generation data available for this plant.
No financial data available for this plant.
Market Position
ISO/RTO Market
MISO
LMP Node
—
Pricing Hub
TEXAS.HUB
Node Source
Shared substation inference
Entergy projects aim to strengthen energy reliability, lower costs
Entergy Texas is increasing electric reliability in Montgomery County with the addition of several major projects in Southeast Texas,...
The career that keeps Southeast Texas moving
Montgomery County Power Station control room operator Scott Nichols. Every time a refinery starts up, a hospital powers critical equipment...
New U.S. electric generating capacity expected to reach a record high in 2026
U.S. power plant developers and operators plan to add 86 gigawatts (GW) of new utility-scale electric generating capacity to the U.S. power...
ERAS Tour: Hi, It’s Me, I’m the Planning Problem
The new ERAS processes in MISO and SPP allow certain power plants to effectively jump the interconnection line, writes Simon Mahan.
Last updated 2026-03-14
View all 10 articles