1.9 MW Solar operating in Harris, TX — Electric Reliability Council of Texas, Inc.
1.9 MW
Nameplate Capacity
1
Generators
unit
Solar Photovoltaic
Technology
2025
Operating Since
Coordinates
29.8251, -95.2471
County
Harris, TX
Nearby Plants
| Field | EIA | GEM | Wikidata |
|---|---|---|---|
| Operator | Catalyze Houston Express Lane Microgrid, LLC | Catalyze Houston Express Lane Microgrid | — |
| Owner(s) | Catalyze Houston Express Lane Microgrid, LLC | — | — |
| Status | Operating | operating | — |
TX Houston 7080 Express Lane is a 1.9 MW solar photovoltaic power plant located in Harris County, Texas. The plant began operating in 2025 and is owned and operated by Catalyze Houston Express Lane Microgrid, LLC. It consists of a single generator utilizing fixed tilt solar tracking technology. The plant's primary fuel source is solar energy.
The facility operates within the Electric Reliability Council of Texas (ERCOT) balancing authority. In its latest year of operation, the plant generated 3 MWh of electricity, resulting in a capacity factor of 0.0%. TX Houston 7080 Express Lane is ranked as the 283rd largest power plant in Texas out of 298, and 5435th nationally out of 7108.
Generated from EIA, GEM, and public data sources
NERC Region
TRE
Balancing Authority
Electric Reliability Council of Texas, Inc.
Grid Voltage
4.8 kV
Regulatory Status
NR
Entity Type
Independent Power Producer
Sector
IPP Non-CHP
0 MWh
Latest Month
3 MWh
Annual Generation
0.0%
Capacity Factor
No financial data available for this plant.
Point of Interconnection
Nearest Substation
Greens Bayou 69kV Substation · 69 kV
Substation Distance
< 10 km
Operator
CenterPoint Energy
Coord Source
OSM spatial
Market Position
ISO/RTO Market
ERCOT
LMP Node
—
Pricing Hub
HB_HOUSTON
Secondary Zone
LZ_HOUSTON
Node Source
Shared substation inference
Substation identified. Node ID not yet resolved against ISO roster.