5 MW Solar operating in Bristol, MA — ISO New England Inc.
5 MW
Nameplate Capacity
1
Generators
unit
Solar Photovoltaic
Technology
2024
Operating Since
Coordinates
41.6211, -71.0553
County
Bristol, MA
Nearby Plants
| Field | EIA | GEM | Wikidata |
|---|---|---|---|
| Operator | AES Clean Energy | AES Clean Energy | — |
| Owner(s) | AES Clean Energy | — | — |
| Status | Operating | operating | — |
Westport Stone & Sand Solar (CSG) is a 5 MW solar photovoltaic power plant located in Bristol County, Massachusetts. The plant began operating in 2024 and is owned and operated by AES Clean Energy. It consists of a single generator utilizing single-axis tracking technology to maximize solar energy capture. The plant's primary fuel source is solar energy (SUN).
In its most recent year of operation, Westport Stone & Sand Solar generated 5,643 MWh of electricity, achieving a capacity factor of 12.8%. The plant operates within the ISO New England Inc. balancing authority and the Northeast Power Coordinating Council (NPCC) NERC region. In terms of size, Westport Stone & Sand Solar ranks as the 27th largest solar facility out of 435 in Massachusetts, and 2733rd nationally out of 7108.
Generated from EIA, GEM, and public data sources
NERC Region
NPCC
Balancing Authority
ISO New England Inc.
Grid Voltage
13.2 kV
Regulatory Status
NR
Entity Type
Independent Power Producer
Sector
IPP Non-CHP
279 MWh
Latest Month
5.6K MWh
Annual Generation
12.8%
Capacity Factor
No financial data available for this plant.
Point of Interconnection
Nearest Substation
Fisher Road Substation · 115 kV
Substation Distance
3.76 km
Operator
Eversource
Coord Source
OSM spatial
Market Position
ISO/RTO Market
ISO-NE
LMP Node
LD.FISHR_RD13.2
Pricing Hub
.H.INTERNAL_HUB
Node Source
Curated node match