21.1 MW Solar operating in Albany, NY — New York Independent System Operator
21.1 MW
Nameplate Capacity
1
Generators
unit
Solar Photovoltaic
Technology
2024
Operating Since
Coordinates
42.5079, -73.8365
County
Albany, NY
Nearby Plants
Owner data does not fully agree across sources.
EIA typically reports the operating utility, while GEM resolves to the financial owner or parent corporation. Both can be correct.
| Field | EIA | GEM | Wikidata |
|---|---|---|---|
| Operator | Greenbacker Renewable Energy Corporation | Greenbacker Renewable Energy Co LLC [100%] | — |
| Owner(s) | Greenbacker Renewable Energy Corporation | Greenbacker Renewable Energy Co LLC [100%] | — |
| Status | Operating | operating | — |
GEM identifies the owner as Greenbacker Renewable Energy Co LLC [100%]
This entity is not yet in the GEM ownership database — chain unavailable.
Hecate Energy Albany 2 LLC is a 21.1 MW solar photovoltaic power plant located in Albany County, New York. The plant began operating in 2024 and has one generator utilizing single-axis solar tracking technology. The primary fuel source is solar (SUN). Greenbacker Renewable Energy Corporation is the operator, and the plant is connected to the New York Independent System Operator (NYISO) balancing authority within the NPCC NERC region.
In its most recent year of operation, the plant generated 24,702 MWh of electricity, achieving a capacity factor of 13.3%. Financial data indicates a power purchase agreement (PPA) price of $63.76 per MWh. Hecate Energy Albany 2 LLC ranks 31st out of 695 power plants in New York and 1343rd out of 7108 plants nationally.
Generated from EIA, GEM, and public data sources
NERC Region
NPCC
Balancing Authority
New York Independent System Operator
Grid Voltage
34.5 kV
Regulatory Status
NR
Entity Type
Independent Power Producer
Sector
IPP Non-CHP
891 MWh
Latest Month
24.7K MWh
Annual Generation
13.3%
Capacity Factor
$78.3/MWh
LCOE (Levelized Cost)
$63.8/MWh
PPA Price
Point of Interconnection
Nearest Substation
BLUE_CIRC_CHEM_DRP
Substation Distance
< 10 km
Coord Source
NYISO direct
Market Position
ISO/RTO Market
NYISO
LMP Node
—
Pricing Hub
NYISO Zone F
Node Source
Shared substation inference
Substation identified. Node ID not yet resolved against ISO roster.
Hecate Energy Sells Up To 2,000 MW Cereza Solar-Plus-Storage Project At DOE’s Hanford Site To Savion, Marking Major Milestone In Large-Scale Energy Campus Strategy
Hecate Energy Transfers 2 GW Hanford Site Cereza Project to Savion as Company Exceeds 12 GW in Projects Sold and Expands Revenue Backlog.
Hecate Energy Sells Up To 2,000 MW Cereza Solar-Plus-Storage Project At DOE’s Hanford Site To Savion, Marking Major Milestone In Large-Scale Energy Campus Strategy
Hecate Energy Transfers 2 GW Hanford Site Cereza Project to Savion as Company Exceeds 12 GW in Projects Sold and Expands Revenue Backlog.
Hecate Energy Sells Up To 2,000 MW Cereza Solar-Plus-Storage Project At DOE’s Hanford Site To Savion, Marking Major Milestone In Large-Scale Energy Campus Strategy
Hecate Energy Transfers 2 GW Hanford Site Cereza Project to Savion as Company Exceeds 12 GW in Projects Sold and Expands Revenue Backlog.
Hecate Energy Sells Up To 2,000 MW Cereza Solar-Plus-Storage Project At DOE’s Hanford Site To Savion, Marking Major Milestone In Large-Scale Energy Campus Strategy
Hecate Energy Transfers 2 GW Hanford Site Cereza Project to Savion as Company Exceeds 12 GW in Projects Sold and Expands Revenue Backlog.
Last updated 2026-03-26
View all 10 articles