74.5 MW Solar operating in Manatee, FL — Florida Power & Light Company
74.5 MW
Nameplate Capacity
1
Generators
unit
Solar Photovoltaic
Technology
2024
Operating Since
Coordinates
27.5793, -82.2606
County
Manatee, FL
Nearby Plants
| Field | EIA | GEM | Wikidata |
|---|---|---|---|
| Operator | Florida Power & Light Co | Florida Power & Light | — |
| Owner(s) | Florida Power & Light Co | NextEra Energy | — |
| Status | Operating | operating | — |
Three Creeks is a 74.5 MW solar photovoltaic power plant located in Manatee County, Florida. The plant began operating in 2024 and utilizes single-axis tracking technology. It is owned by NextEra Energy and operated by Florida Power & Light Co. Three Creeks is ranked as the 57th largest power plant in Florida out of 227, and 868th nationally out of 7108. The plant operates within the Florida Power & Light Company balancing authority, within the SERC NERC region.
In its most recent year of operation, Three Creeks generated 174,861 MWh of electricity, achieving a capacity factor of 26.8%. Financial data indicates an installed cost of $1,440 per kW, according to FERC filings.
Generated from EIA, GEM, and public data sources
NERC Region
SERC
Balancing Authority
Florida Power & Light Company
Grid Voltage
230 kV
Regulatory Status
RE
Entity Type
Investor-Owned Utility
Sector
Electric Utility
12.2K MWh
Latest Month
174.9K MWh
Annual Generation
26.8%
Capacity Factor
$1,440/kW
Installed Cost
$0.4/MWh
Operating Cost
Florida Power & Light Company
Reporting Utility
Annual Capital & Operating Expenses
This plant is outside organized wholesale electricity markets (ISOs/RTOs). Nodal pricing data is not available.
Nearly $100 million invested as developer continues buying spree along Salt Creek in south St. Pete
three-story office building recently purhcased by prometheus Partners for $28.2 million | loopnet. Clearwater-based real estate firm...
Duke Energy Submits Early Site Permit at Coal Plant Site
Duke Energy Submits Early Site Permit at Coal Plant Site Wyoming Awards $100 Million for BWXT TRISO Fuel Plant Centrus Launches Commercial...
We Energies hopes to add almost 3GW to the electric grid to help meet data center demand
To meet expected surges in energy demand from data centers, We Energies is asking state regulators to approve a multi-billion-dollar plan to...
A coal power plant in Texas, America’s newest, set to stay idle until 2027
The Sandy Creek Energy Station is America's newest coal-fired power plant, and it's expected to remain offline until 2027.
Last updated 2026-03-14