5 MW Solar operating in Moore, NC — Duke Energy Progress East
5 MW
Nameplate Capacity
1
Generators
unit
Solar Photovoltaic
Technology
2019
Operating Since
Coordinates
35.2140, -79.5558
County
Moore, NC
Nearby Plants
| Field | EIA | GEM | Wikidata |
|---|---|---|---|
| Operator | Strata Manager, LLC | Strata Manager | — |
| Owner(s) | Gladstone Farm, LLC | Gladstone Farm LLC [100%] | — |
| Status | Operating | operating | — |
GEM identifies the owner as Gladstone Farm LLC [100%]
This entity is not yet in the GEM ownership database — chain unavailable.
Gladstone Farm is a 5 MW solar photovoltaic power plant located in Moore County, North Carolina. The plant began operating in 2019 and has a single generator. Strata Manager, LLC is the plant's operator, according to the EIA. The facility utilizes single-axis tracking to maximize solar energy capture. Gladstone Farm is interconnected to the Duke Energy Progress East balancing authority within the SERC NERC region.
In its most recent year of operation, Gladstone Farm generated 10,805 MWh of electricity, achieving a capacity factor of 24.6%. The plant is ranked as the 164th largest solar facility in North Carolina out of 770, and 2293rd nationally out of 7108. The plant's primary fuel source is solar energy (SUN).
Generated from EIA, GEM, and public data sources
NERC Region
SERC
Balancing Authority
Duke Energy Progress East
Grid Voltage
22.86 kV
Regulatory Status
NR
Entity Type
Independent Power Producer
Sector
IPP Non-CHP
522 MWh
Latest Month
10.8K MWh
Annual Generation
24.6%
Capacity Factor
No financial data available for this plant.
This plant is outside organized wholesale electricity markets (ISOs/RTOs). Nodal pricing data is not available.