111.8 MW Wind operating in Broome, NY — New York Independent System Operator
111.8 MW
Nameplate Capacity
1
Generators
unit
Onshore Wind Turbine
Technology
2023
Operating Since
Coordinates
42.0943, -75.5126
County
Broome, NY
Nearby Plants
Owner data does not fully agree across sources.
EIA typically reports the operating utility, while GEM resolves to the financial owner or parent corporation. Both can be correct.
| Field | EIA | GEM | Wikidata |
|---|---|---|---|
| Operator | Bluestone Wind, LLC | Northland Power Inc [100%] | — |
| Owner(s) | Bluestone Wind, LLC | Northland Power | — |
| Status | Operating | operating | — |
Bluestone Wind, LLC is a 111.8 MW wind power plant located in Broome County, New York. The facility began operating in 2023 and is owned and operated by Bluestone Wind, LLC, a subsidiary of the Canadian company Northland Power. The plant utilizes a single generator consisting of onshore wind turbines. The turbines have a hub height of 120 meters and a rotor diameter of 150 meters, and are manufactured by Vestas, model V150-4.3.
The plant operates within the New York Independent System Operator (NYISO) balancing authority and the Northeast Power Coordinating Council (NPCC) NERC region. In its most recent year of operation, Bluestone Wind generated 331,379 MWh of electricity, achieving a capacity factor of 33.8%. Bluestone Wind ranks as the 14th largest wind farm in New York out of 22, and 639th nationally out of 734.
Generated from EIA, GEM, and public data sources
NERC Region
NPCC
Balancing Authority
New York Independent System Operator
Grid Voltage
115 kV
Regulatory Status
NR
Entity Type
Independent Power Producer
Sector
IPP Non-CHP
Bluestone Wind
39.6K MWh
Latest Month
331.4K MWh
Annual Generation
33.8%
Capacity Factor
No financial data available for this plant.
Market Position
ISO/RTO Market
NYISO
LMP Node
BLUESTONE___WT_PWR
Pricing Hub
NYISO Zone E
Node Source
Curated node match
2025 Q4 MD&A
Our Global Footprint. 12. Built for Long-Term Value. 13. Our Strategy. 14. Project Updates. 20. Management's Discussion and Analysis.
Local opposition, permitting struggles stall progress on Northland Power's 1GWh BESS in New York
Some independent power producers (IPP) are still struggling to make progress in the face of local opposition, permitting hurdles and moratoriums.
Hanover rejects battery storage project
The Town Board unanimously voted to reject the proposed battery energy storage system from Northland Power, along with any similar projects of its kind.
Hanover discusses battery storage proposal
The proposed 250 megawatt lithium-ion battery storage project would be owned by Northland Power, Inc., the same owner as the Ball Hill Wind Turbine project.
Last updated 2026-03-14