1.5 MW Natural Gas operating in Jasper, IN — Midcontinent Independent Transmission System Operator, Inc..
1.5 MW
Nameplate Capacity
1
Generators
unit
Natural Gas Internal Combustion Engine
Technology
2023
Operating Since
Coordinates
41.0864, -87.2568
County
Jasper, IN
Nearby Plants
| Field | EIA | GEM | Wikidata |
|---|---|---|---|
| Operator | Herrema Dairy, LLC | — | — |
| Owner(s) | Herrema Dairy, LLC | — | — |
| Status | Operating | — | — |
Herrema Dairy is a natural gas-fired power plant located in Jasper County, Indiana. The plant, owned and operated by Herrema Dairy, LLC, has a total capacity of 1.5 MW. It commenced operations in 2023 and utilizes a single natural gas internal combustion engine generator. The plant operates within the Midcontinent Independent Transmission System Operator, Inc. (MISO) balancing authority and the ReliabilityFirst Corporation (RFC) NERC region.
In its most recent year of operation, Herrema Dairy generated 7,155 MWh of electricity, achieving a capacity factor of 54.3%. The plant is ranked 39th out of 41 power plants in Indiana based on capacity, and 1773rd out of 1963 plants nationally.
Generated from EIA, GEM, and public data sources
NERC Region
RFC
Balancing Authority
Midcontinent Independent Transmission System Operator, Inc..
Grid Voltage
12 kV
Regulatory Status
NR
Entity Type
Industrial
Sector
Industrial Non-CHP
614 MWh
Latest Month
7.2K MWh
Annual Generation
54.3%
Capacity Factor
No financial data available for this plant.
Point of Interconnection
Nearest Substation
Fair Oaks Substation · 69 kV
Substation Distance
< 10 km
Operator
Jasper County REMC
Coord Source
OSM spatial
Market Position
ISO/RTO Market
MISO
LMP Node
—
Pricing Hub
INDIANA.HUB
Node Source
OSM spatial match
Substation identified. Node ID not yet resolved against ISO roster.