16.4 MW Solar planned in York, ME — ISO New England Inc.
16.4 MW
Nameplate Capacity
1
Generators
unit
Solar Photovoltaic
Technology
Planned: —
Planned Operation
Coordinates
43.6434, -70.5584
County
York, ME
Nearby Plants
| Field | EIA | GEM | Wikidata |
|---|---|---|---|
| Operator | Emery Meadow Solar Station, LLC | Emery Meadow Solar Station | — |
| Owner(s) | Emery Meadow Solar Station, LLC | — | — |
| Status | Planned | pre-construction | — |
Emery Meadow Solar Station is a 16.4 MW solar photovoltaic power plant located in York County, Maine. The plant, identified by plant ID 65366, is owned and operated by Emery Meadow Solar Station, LLC. It consists of a single generator utilizing fixed-tilt solar tracking technology. The primary fuel source for the facility is solar energy (SUN).
The plant operates within the ISO New England Inc. balancing authority and the Northeast Power Coordinating Council (NPCC) NERC region. Emery Meadow Solar Station is ranked as the 13th largest solar facility in Maine out of 153, and nationally it holds a rank of 1634 out of 7108 solar plants. Recent news coverage related to the plant has focused on regulatory matters.
Generated from EIA, GEM, and public data sources
NERC Region
NPCC
Balancing Authority
ISO New England Inc.
Grid Voltage
34.5 kV
Regulatory Status
NR
Entity Type
Independent Power Producer
Sector
IPP Non-CHP
No generation data available for this plant.
No financial data available for this plant.
Point of Interconnection
Nearest Substation
Buxton Substation · 345 kV
Substation Distance
< 10 km
Operator
Central Maine Power Company
Coord Source
OSM spatial
Market Position
ISO/RTO Market
ISO-NE
LMP Node
LD.W_BUXTON34.5
Pricing Hub
.Z.MAINE
Node Source
EIA-860 direct report
CMP switchyard expansion OK’d in Buxton
The project still need approval from the Maine Department of Environmental Protection and the Army Corps of Engineers before it can proceed.
Last updated 2026-03-14