74.5 MW Solar operating in Okeechobee, FL — Florida Power & Light Company
74.5 MW
Nameplate Capacity
1
Generators
unit
Solar Photovoltaic
Technology
2021
Operating Since
Coordinates
27.6175, -80.7922
County
Okeechobee, FL
Nearby Plants
Owner data does not fully agree across sources.
EIA typically reports the operating utility, while GEM resolves to the financial owner or parent corporation. Both can be correct.
| Field | EIA | GEM | Wikidata |
|---|---|---|---|
| Operator | Florida Power & Light Co | Florida Power & Light | — |
| Owner(s) | Florida Power & Light Co | NextEra Energy | — |
| Status | Operating | operating | — |
The Fort Drum Energy Center is a 74.5 MW solar photovoltaic power plant located in Okeechobee County, Florida. The plant began operating in 2021 and has one generator. It is owned by NextEra Energy and operated by Florida Power & Light Co. The plant uses fixed-tilt solar tracking technology.
In its most recent year of operation, the Fort Drum Energy Center generated 137,900 MWh of electricity, achieving a capacity factor of 21.1%. The plant's installed cost was $945 per kW, according to FERC data. Fort Drum Energy Center is ranked 37th out of 227 power plants in Florida, and 849th nationally out of 7108 plants. The balancing authority for the plant is Florida Power & Light Company, and it is located within the SERC NERC region.
Generated from EIA, GEM, and public data sources
NERC Region
SERC
Balancing Authority
Florida Power & Light Company
Grid Voltage
500 kV
Regulatory Status
RE
Entity Type
Investor-Owned Utility
Sector
Electric Utility
6.8K MWh
Latest Month
137.9K MWh
Annual Generation
21.1%
Capacity Factor
$1,153/kW
Installed Cost
$1.0/MWh
Operating Cost
Florida Power & Light Company
Reporting Utility
Annual Capital & Operating Expenses
Cumulative Installed Cost
Per-Unit Cost Trends
This plant is outside organized wholesale electricity markets (ISOs/RTOs). Nodal pricing data is not available.
Mystery site for 4.3-gigawatt energy hub has southwestern Pennsylvania officials wondering
NextEra Energy Transmission MidAtlantic plans a 107.5-mile power line through Greene and Fayette counties as the company scouts sites for a...
Spud Valley solar project on track to build in Alamosa County
NextEra Energy Resource's impressive solar project called Spud Valley Energy Center is making its way through the process at Alamosa County...
Uproar Over Reduced Permit Fees for Solar Developers in Oklahoma
NextEra Energy's 2,000-acre solar farm under construction in northwest Oklahoma is set to become one of the state's largest renewable energy...
NextEra Highlights Arkansas Investments as Ashdown Solar Plans Take Shape
NextEra Energy Resources says its planned Little Ashdown Solar project will bring jobs, tax revenue and clean energy to Little River County...
Last updated 2026-03-26
View all 10 articles