20 MW Solar operating in Buckingham, VA — PJM Interconnection, LLC
20 MW
Nameplate Capacity
1
Generators
unit
Solar Photovoltaic
Technology
2021
Operating Since
Coordinates
37.5064, -78.3810
County
Buckingham, VA
Nearby Plants
Owner data does not fully agree across sources.
EIA typically reports the operating utility, while GEM resolves to the financial owner or parent corporation. Both can be correct.
| Field | EIA | GEM | Wikidata |
|---|---|---|---|
| Operator | Energix Buckingham, LLC | Energix Renewable Energies | — |
| Owner(s) | Energix Buckingham, LLC | Energix Renewable Energies Ltd [100%] | — |
| Status | Operating | operating | — |
GEM identifies the owner as Energix Renewable Energies Ltd [100%]
This entity is not yet in the GEM ownership database — chain unavailable.
Energix Buckingham, LLC is a 20 MW solar photovoltaic power plant located in Buckingham County, Virginia. The plant began operating in 2021 and has one generator. It is owned and operated by Energix Buckingham, LLC. The primary fuel source is solar (SUN). The plant utilizes single-axis tracking technology to maximize solar energy capture.
The plant operates within the PJM Interconnection, LLC balancing authority and the SERC NERC region. In its latest year of operation, the plant generated 40,282 MWh of electricity, achieving a capacity factor of 22.9%. Energix Buckingham, LLC is ranked 86th out of 168 power plants in Virginia and 1513th out of 7108 plants nationally. Financial data is available for the plant from LBNL, and the plant has been featured in two news articles, one regulatory and one industry-related.
Generated from EIA, GEM, and public data sources
NERC Region
SERC
Balancing Authority
PJM Interconnection, LLC
Grid Voltage
34.5 kV
Regulatory Status
NR
Entity Type
Independent Power Producer
Sector
IPP Non-CHP
Buckingham IIK
1.6K MWh
Latest Month
40.3K MWh
Annual Generation
22.9%
Capacity Factor
$39.1/MWh
LCOE (Levelized Cost)
$32.2/MWh
Energy Value
Point of Interconnection
Nearest Substation
Buckingham Substation · 230 kV
Substation Distance
< 10 km
Operator
Virginia Electric and Power Company
Coord Source
OSM spatial
Market Position
ISO/RTO Market
PJM
LMP Node
34964545
Pricing Hub
DOMINION HUB
Node Source
EIA-860 direct report
Gabriel Solar goes to a vote: County makes decision on project
The numbers didn't match up. When employees from Gabriel Solar LLC came to argue their case Tuesday night, sometimes ...
Solar firm Energix fined again for Virginia environmental violations
The latest order from the state Department of Environmental Quality marks the third year in a row that the company has faced civil...
Last updated 2026-03-14
View all articles