10 MW Solar operating in Lake, OR — Bonneville Power Administration
10 MW
Nameplate Capacity
1
Generators
unit
Solar Photovoltaic
Technology
2020
Operating Since
Coordinates
43.3961, -120.9490
County
Lake, OR
Nearby Plants
| Field | EIA | GEM | Wikidata |
|---|---|---|---|
| Operator | SC Oregon 2 Lessor Parent, LLC | NES Euryalus | — |
| Owner(s) | SC Oregon 2 Lessor Parent, LLC | SC Oregon 2 Lessor Parent LLC [100%] | — |
| Status | Operating | operating | — |
GEM identifies the owner as SC Oregon 2 Lessor Parent LLC [100%]
This entity is not yet in the GEM ownership database — chain unavailable.
Rock Garden Solar, LLC is a 10 MW solar photovoltaic power plant located in Lake County, Oregon. The plant began operating in 2020 and has one generator. It is owned and operated by SC Oregon 2 Lessor Parent, LLC. The facility's primary fuel source is the sun, and it utilizes single-axis solar tracking technology. Rock Garden Solar is connected to the Bonneville Power Administration balancing authority within the Western Electricity Coordinating Council (WECC) NERC region.
In its most recent year of operation, Rock Garden Solar generated 24,563 MWh of electricity, achieving a capacity factor of 27.9%. The plant ranks as the 18th largest solar facility in Oregon out of 147, and 1841st nationally out of 7108. Financial data is available for the plant from LBNL, though specific metrics are not provided.
Generated from EIA, GEM, and public data sources
NERC Region
WECC
Balancing Authority
Bonneville Power Administration
Grid Voltage
115 kV
Regulatory Status
NR
Entity Type
Independent Power Producer
Sector
IPP Non-CHP
766 MWh
Latest Month
24.6K MWh
Annual Generation
27.9%
Capacity Factor
$53.0/MWh
LCOE (Levelized Cost)
$26.4/MWh
Energy Value
This plant is outside organized wholesale electricity markets (ISOs/RTOs). Nodal pricing data is not available.
Hyperscale data center gains rezoning vote after hours of opposing testimony
Jan. 7, 2026. A crowd larger and more passionate than many can remember seeing at a Sioux Falls City Council meeting Tuesday tried to fight the city's first...
Massive data storage facility on fast track
Palm Beach County Zoning Commission approves plans to allow nearly 1.8 million square feet of data storage on Southern Boulevard despite...
Energy Giant Proposes 10-Acre Battery Facility in Rural Hillsboro Next To Homes
A Texas-based energy developer, Jupiter Power LLC, has quietly filed plans with Washington County to build a massive 10-acre Battery Energy...
Energy Giant Proposes 10-Acre Battery Facility in Rural Hillsboro Next To Homes
A Texas-based energy developer, Jupiter Power LLC, has quietly filed plans with Washington County to build a massive 10-acre Battery Energy...
Last updated 2026-03-14
View all 10 articles