6.2 MW Batteries (3 MW) + Solar Photovoltaic (4 MW) operating in Hampden, MA — ISO New England Inc.
6.2 MW
Nameplate Capacity
2
Generators
units
Hybrid (2)
Technology
Batteries + Solar Photovoltaic
2021
Operating Since
Coordinates
42.0587, -72.6915
County
Hampden, MA
Nearby Plants
| Field | EIA | GEM | Wikidata |
|---|---|---|---|
| Operator | CES Agawam Tuckahoe Solar LLC | CES Agawam Tuckahoe Solar | — |
| Owner(s) | CES Agawam Tuckahoe Solar LLC | — | — |
| Status | Operating | operating | — |
The CES Agawam Tuckahoe Solar Hybrid plant is a 6.2 MW hybrid power plant located in Hampden County, Massachusetts. The plant, which came online in 2021, is owned and operated by CES Agawam Tuckahoe Solar LLC. It ranks 55th in size among Massachusetts power plants and 931st nationally. The facility is a hybrid plant, utilizing both solar photovoltaic generation and battery energy storage. It operates within the ISO New England Inc. balancing authority and the NPCC NERC region.
The plant's battery energy storage system (BESS) has a capacity of 5.2 MWh and a duration of 2 hours, utilizing lithium-ion battery chemistry (LIB). The solar array uses a fixed-tilt tracking system. In its most recent year of operation, the plant generated 6,774 MWh of electricity, resulting in a capacity factor of 12.4%. The plant consists of two generators and its primary fuel is listed as MWH.
Generated from EIA, GEM, and public data sources
NERC Region
NPCC
Balancing Authority
ISO New England Inc.
Grid Voltage
13.8 kV
Regulatory Status
NR
Entity Type
Independent Power Producer
Sector
IPP Non-CHP
380 MWh
Latest Month
6.8K MWh
Annual Generation
12.4%
Capacity Factor
No financial data available for this plant.
Point of Interconnection
Nearest Substation
South Agawam Switching Station · 115 kV
Substation Distance
3.759 km
Operator
Eversource
Coord Source
OSM spatial
Market Position
ISO/RTO Market
ISO-NE
LMP Node
UN.BERK_PWR21 BERK
Pricing Hub
.H.INTERNAL_HUB
Node Source
Curated node match