2 MW Solar operating in Robeson, NC — Duke Energy Progress East
2 MW
Nameplate Capacity
1
Generators
unit
Solar Photovoltaic
Technology
2020
Operating Since
Coordinates
34.6626, -79.1329
County
Robeson, NC
Nearby Plants
| Field | EIA | GEM | Wikidata |
|---|---|---|---|
| Operator | North Carolina El Member Corp | North Carolina Electric Membership | — |
| Owner(s) | North Carolina El Member Corp | — | — |
| Status | Operating | operating | — |
Holly Swamp Solar, LLC is a 2 MW solar photovoltaic power plant located in Robeson County, North Carolina. The plant began operating in 2020 and has a single generator. It is owned and operated by North Carolina Electric Membership Corporation. The facility utilizes single-axis tracking to maximize solar energy capture.
The plant's latest annual generation was 4,329 MWh, resulting in a capacity factor of 24.6%. Holly Swamp Solar operates within the Duke Energy Progress East balancing authority and is part of the SERC NERC region. In terms of size, the plant is ranked 707 out of 770 power plants in North Carolina, and 5272 out of 7108 nationally.
Generated from EIA, GEM, and public data sources
NERC Region
SERC
Balancing Authority
Duke Energy Progress East
Grid Voltage
12.47 kV
Regulatory Status
RE
Entity Type
Cooperative
Sector
Electric Utility
235 MWh
Latest Month
4.3K MWh
Annual Generation
24.6%
Capacity Factor
No financial data available for this plant.