1 MW Solar operating in McLeod, MN — Midcontinent Independent Transmission System Operator, Inc..
1 MW
Nameplate Capacity
1
Generators
unit
Solar Photovoltaic
Technology
2021
Operating Since
Coordinates
44.7249, -94.4958
County
McLeod, MN
Nearby Plants
| Field | EIA | GEM | Wikidata |
|---|---|---|---|
| Operator | Nautilus Solar Solutions | Nautilus Solar Solutions | — |
| Owner(s) | Nautilus Solar Solutions | — | — |
| Status | Operating | operating | — |
Stewart CSG1, LLC is a 1 MW solar photovoltaic power plant located in McLeod County, Minnesota. The plant, which began operating in 2021, is owned and operated by Nautilus Solar Solutions. It utilizes a single-axis tracking system to maximize solar energy capture. The plant is interconnected to the Midcontinent Independent Transmission System Operator (MISO) grid and falls within the MRO NERC region.
In its most recent year of operation, Stewart CSG1 generated 2,189 MWh of electricity, achieving a capacity factor of 24.9%. This output ranks the facility as the 405th largest power plant in Minnesota out of 540, and 6832nd nationally out of 7108. The plant has one generator and its primary fuel source is solar energy.
Generated from EIA, GEM, and public data sources
NERC Region
MRO
Balancing Authority
Midcontinent Independent Transmission System Operator, Inc..
Grid Voltage
13.8 kV
Regulatory Status
NR
Entity Type
Independent Power Producer
Sector
IPP Non-CHP
55 MWh
Latest Month
2.2K MWh
Annual Generation
24.9%
Capacity Factor
No financial data available for this plant.
Market Position
ISO/RTO Market
MISO
LMP Node
—
Pricing Hub
MINN.HUB
Node Source
OSM spatial match