1.1 MW Solar operating in Weld, CO — Western Area Power Administration - Rocky Mountain Region
1.1 MW
Nameplate Capacity
1
Generators
unit
Solar Photovoltaic
Technology
2019
Operating Since
Coordinates
40.5775, -104.8971
County
Weld, CO
Nearby Plants
| Field | EIA | GEM | Wikidata |
|---|---|---|---|
| Operator | SR Skylark C, LLC | SR Skylark C | — |
| Owner(s) | SR Skylark C, LLC | — | — |
| Status | Operating | operating | — |
SR Skylark C is a 1.1 MW solar photovoltaic power plant located in Weld County, Colorado. The plant began operating in 2019 and is owned and operated by SR Skylark C, LLC. It consists of a single generator utilizing single-axis tracking technology to maximize solar energy capture. The plant's output is managed within the Western Area Power Administration - Rocky Mountain Region balancing authority, situated within the Western Electricity Coordinating Council (WECC) NERC region.
In its most recent year of operation, SR Skylark C generated 2,344 MWh of electricity, achieving a capacity factor of 24.3%. Relative to other power plants in Colorado, SR Skylark C ranks 166th in size out of 177 plants. Nationally, it is ranked 6262nd out of 7108 plants. The plant's primary fuel source is solar energy.
Generated from EIA, GEM, and public data sources
NERC Region
WECC
Balancing Authority
Western Area Power Administration - Rocky Mountain Region
Grid Voltage
13.5 kV
Regulatory Status
NR
Entity Type
Independent Power Producer
Sector
IPP Non-CHP
109 MWh
Latest Month
2.3K MWh
Annual Generation
24.3%
Capacity Factor
No financial data available for this plant.
This plant is outside organized wholesale electricity markets (ISOs/RTOs). Nodal pricing data is not available.