3 MW Solar operating in Sussex, DE — PJM Interconnection, LLC
3 MW
Nameplate Capacity
1
Generators
unit
Solar Photovoltaic
Technology
2019
Operating Since
Coordinates
38.6645, -75.3991
County
Sussex, DE
Nearby Plants
| Field | EIA | GEM | Wikidata |
|---|---|---|---|
| Operator | Luminace Solar MC, LLC | Luminace Solar MC | — |
| Owner(s) | Luminace Solar MC, LLC | — | — |
| Status | Operating | operating | — |
DEC Phase II at Georgetown is a 3 MW solar photovoltaic power plant located in Sussex County, Delaware. The plant began operating in 2019 and has one generator. Luminace Solar MC, LLC is the owner and operator. The facility utilizes a fixed tilt solar tracking system.
The plant's latest annual generation was 5,373 MWh, resulting in a capacity factor of 20.4%. DEC Phase II at Georgetown is interconnected to the PJM Interconnection, LLC balancing authority, within the RFC NERC region. It is ranked as the 13th largest solar plant in Delaware out of 22, and 3990th nationally out of 7108.
Generated from EIA, GEM, and public data sources
NERC Region
RFC
Balancing Authority
PJM Interconnection, LLC
Grid Voltage
12.47 kV
Regulatory Status
NR
Entity Type
Independent Power Producer
Sector
IPP Non-CHP
321 MWh
Latest Month
5.4K MWh
Annual Generation
20.4%
Capacity Factor
No financial data available for this plant.
Point of Interconnection
Nearest Substation
Pepper Substation · 69 kV
Substation Distance
1.226 km
Operator
Delaware Electric Cooperative
Coord Source
OSM spatial
Market Position
ISO/RTO Market
PJM
LMP Node
PEPPER 69 KV PEPPER
Pricing Hub
WESTERN HUB
Location Type
Load Node
Node Source
Curated node match