2.3 MW Solar operating in Bristol, MA — ISO New England Inc.
2.3 MW
Nameplate Capacity
1
Generators
unit
Solar Photovoltaic
Technology
2019
Operating Since
Coordinates
41.9304, -71.0604
County
Bristol, MA
Nearby Plants
| Field | EIA | GEM | Wikidata |
|---|---|---|---|
| Operator | Green Street Power Partners | Green Street Power Partners | — |
| Owner(s) | Green Street Power Partners | — | — |
| Status | Operating | operating | — |
GSPP Raynham TMLP, LLC CSG is a 2.3 MW solar photovoltaic power plant located in Bristol County, Massachusetts. The plant began operating in 2019 and has one generator. It is owned and operated by Green Street Power Partners. The plant's primary fuel source is solar (SUN).
In its most recent year of operation, GSPP Raynham TMLP, LLC CSG generated 3,629 MWh of electricity, achieving a capacity factor of 18.0%. The solar array utilizes a fixed tilt tracking system. The plant operates within the ISO New England Inc. balancing authority and the NPCC NERC region. In terms of size, the plant ranks 194th out of 435 power plants in Massachusetts and 4428th out of 7108 plants nationally.
Generated from EIA, GEM, and public data sources
NERC Region
NPCC
Balancing Authority
ISO New England Inc.
Grid Voltage
13.2 kV
Regulatory Status
NR
Entity Type
Commercial
Sector
IPP Non-CHP
152 MWh
Latest Month
3.6K MWh
Annual Generation
18.0%
Capacity Factor
No financial data available for this plant.
Point of Interconnection
Nearest Substation
Raynham Substation · 115 kV
Substation Distance
< 10 km
Operator
Taunton Municipal Lighting Plant
Coord Source
OSM spatial
Market Position
ISO/RTO Market
ISO-NE
LMP Node
—
Pricing Hub
.H.INTERNAL_HUB
Node Source
OSM spatial match
Substation identified. Node ID not yet resolved against ISO roster.