74.5 MW Solar operating in Hendry, FL — Florida Power & Light Company
74.5 MW
Nameplate Capacity
1
Generators
unit
Solar Photovoltaic
Technology
2020
Operating Since
Coordinates
26.7010, -81.1376
County
Hendry, FL
Nearby Plants
Owner data does not fully agree across sources.
EIA typically reports the operating utility, while GEM resolves to the financial owner or parent corporation. Both can be correct.
| Field | EIA | GEM | Wikidata |
|---|---|---|---|
| Operator | Florida Power & Light Co | Florida Power & Light | — |
| Owner(s) | Florida Power & Light Co | NextEra Energy | — |
| Status | Operating | operating | — |
Blue Heron Solar is a 74.5 MW solar photovoltaic power plant located in Hendry County, Florida. The plant began operating in 2020 and has one generator. It is owned by NextEra Energy and operated by Florida Power & Light Co. The primary fuel source is solar, and the plant utilizes fixed-tilt solar tracking technology. Blue Heron Solar is ranked 131st out of 227 power plants in Florida and 944th out of 7108 plants nationally.
In its most recent year of operation, Blue Heron Solar generated 154,302 MWh of electricity, achieving a capacity factor of 23.6%. The plant operates within the Florida Power & Light Company balancing authority and the SERC NERC region. Financial data indicates an installed cost of $1,134.09 per kW, as reported to FERC.
Generated from EIA, GEM, and public data sources
NERC Region
SERC
Balancing Authority
Florida Power & Light Company
Grid Voltage
230 kV
Regulatory Status
RE
Entity Type
Investor-Owned Utility
Sector
Electric Utility
12.0K MWh
Latest Month
154.3K MWh
Annual Generation
23.6%
Capacity Factor
$1,137/kW
Installed Cost
$2.0/MWh
Operating Cost
Florida Power & Light Company
Reporting Utility
Annual Capital & Operating Expenses
Cumulative Installed Cost
Per-Unit Cost Trends
This plant is outside organized wholesale electricity markets (ISOs/RTOs). Nodal pricing data is not available.
Mystery site for 4.3-gigawatt energy hub has southwestern Pennsylvania officials wondering
NextEra Energy Transmission MidAtlantic plans a 107.5-mile power line through Greene and Fayette counties as the company scouts sites for a...
Spud Valley solar project on track to build in Alamosa County
NextEra Energy Resource's impressive solar project called Spud Valley Energy Center is making its way through the process at Alamosa County...
Uproar Over Reduced Permit Fees for Solar Developers in Oklahoma
NextEra Energy's 2,000-acre solar farm under construction in northwest Oklahoma is set to become one of the state's largest renewable energy...