250 MW Wind operating in Fisher, TX — Electric Reliability Council of Texas, Inc.
250 MW
Nameplate Capacity
1
Generators
unit
Onshore Wind Turbine
Technology
2020
Operating Since
Coordinates
32.9867, -100.5522
County
Fisher, TX
Nearby Plants
Owner data does not fully agree across sources.
EIA typically reports the operating utility, while GEM resolves to the financial owner or parent corporation. Both can be correct.
| Field | EIA | GEM | Wikidata |
|---|---|---|---|
| Operator | Amadeus Wind LLC | BayWa R.E. | — |
| Owner(s) | Amadeus Wind LLC | Fengate Asset Management [100%] | — |
| Status | Operating | operating | — |
GEM identifies the owner as Fengate Asset Management [100%]
This entity is not yet in the GEM ownership database — chain unavailable.
Amadeus Wind Farm is a 250 MW wind power plant located in Fisher County, Texas. The facility began operating in 2020 and is owned and operated by Amadeus Wind LLC. The plant utilizes a single generator consisting of multiple onshore wind turbines. The wind turbines have a hub height of 80 meters and a rotor diameter of 100 meters, and were manufactured by GE Wind, model GE1.79-100.
In its most recent year of operation, Amadeus Wind Farm generated 716,480 MWh of electricity, achieving a capacity factor of 32.7%. The plant is interconnected to the Electric Reliability Council of Texas, Inc. (ERCOT) balancing authority, within the Texas Reliability Entity (TRE) NERC region. Amadeus Wind Farm ranks as the 53rd largest wind farm in Texas out of 200, and 164th nationally out of 734 wind farms.
Generated from EIA, GEM, and public data sources
NERC Region
TRE
Balancing Authority
Electric Reliability Council of Texas, Inc.
Grid Voltage
345 kV
Regulatory Status
NR
Entity Type
Independent Power Producer
Sector
IPP Non-CHP
70.2K MWh
Latest Month
716.5K MWh
Annual Generation
32.7%
Capacity Factor
No financial data available for this plant.
Point of Interconnection
Nearest Substation
Mozart Substation · 69 kV
Substation Distance
0 km
Operator
BayWa
Coord Source
OSM spatial
Market Position
ISO/RTO Market
ERCOT
LMP Node
AMADEUS_ALL
Pricing Hub
HB_WEST
Secondary Zone
LZ_WEST
Location Type
Resource Node
Node Source
Curated node match
Fire Weather Watch: Parmer; Castro; Swisher; Briscoe; Hall; Childress; Bailey; Lamb; Hale; Floyd; Motley; Cottle; Cochra
The Fire Weather Watch has been replaced. Please see the latest information from NWS Lubbock TX on this developing situation.
Fire Weather Watch: Parmer; Castro; Swisher; Briscoe; Hall; Childress; Bailey; Lamb; Hale; Floyd; Motley; Cottle; Cochra
Fire Weather Watch issued March 20 at 10:32PM CDT until March 22 at 9:00PM CDT by NWS Lubbock TX
Red Flag Warning: Parmer; Castro; Swisher; Briscoe; Hall; Childress; Bailey; Lamb; Hale; Floyd; Motley; Cottle; Cochra
Red Flag Warning issued March 20 at 10:32PM CDT until March 21 at 8:00PM CDT by NWS Lubbock TX
BayWa r.e. Completes Construction of 250 MW Amadeus Wind Farm in Texas
PRNewswire/ -- BayWa r.e. has completed construction and achieved financial close of the Amadeus Wind project in Texas.
Last updated 2026-03-21