4.1 MW Solar operating in Somerset, ME — ISO New England Inc.
4.1 MW
Nameplate Capacity
1
Generators
unit
Solar Photovoltaic
Technology
2017
Operating Since
Coordinates
44.8040, -69.8380
County
Somerset, ME
Nearby Plants
| Field | EIA | GEM | Wikidata |
|---|---|---|---|
| Operator | Madison Energy Holdings LLC | IGS ORIX Solar I | — |
| Owner(s) | Madison Energy Holdings LLC | — | — |
| Status | Operating | operating | — |
IOS - MEW Phase 1 is a solar photovoltaic power plant located in Somerset County, Maine. The plant, owned and operated by Madison Energy Holdings LLC, has a total capacity of 4.1 MW. It commenced operations in 2017 and consists of a single generator utilizing fixed-tilt solar tracking technology. The plant's primary fuel source is solar energy.
In its most recent year of operation, IOS - MEW Phase 1 generated 1,026 MWh of electricity, resulting in a capacity factor of 2.8%. The plant operates within the ISO New England Inc. balancing authority and the Northeast Power Coordinating Council (NPCC) NERC region. In terms of size, IOS - MEW Phase 1 ranks as the 91st largest power plant in Maine out of 153, and 3365th nationally out of 7108.
Generated from EIA, GEM, and public data sources
NERC Region
NPCC
Balancing Authority
ISO New England Inc.
Grid Voltage
12.47 kV
Regulatory Status
NR
Entity Type
Independent Power Producer
Sector
IPP Non-CHP
261 MWh
Latest Month
1.0K MWh
Annual Generation
2.8%
Capacity Factor
No financial data available for this plant.
Point of Interconnection
Nearest Substation
Madison Substation · 115 kV
Substation Distance
< 10 km
Operator
Madison Electric Works
Coord Source
OSM spatial
Market Position
ISO/RTO Market
ISO-NE
LMP Node
—
Pricing Hub
.Z.MAINE
Node Source
Shared substation inference
Substation identified. Node ID not yet resolved against ISO roster.