30 MW BESS operating in San Diego, CA — California Independent System Operator
30 MW
Nameplate Capacity
1
Generators
unit
Batteries
Technology
2017
Operating Since
Coordinates
33.1244, -117.1143
County
San Diego, CA
Nearby Plants
| Field | EIA | GEM | Wikidata |
|---|---|---|---|
| Operator | San Diego Gas & Electric Co | San Diego Gas & Electric | — |
| Owner(s) | San Diego Gas & Electric Co | Sempra Energy | — |
| Status | Operating | — | — |
Escondido Energy Storage is a 30 MW battery energy storage system located in San Diego County, California. The plant began operating in 2017 and is owned by Sempra Energy, with San Diego Gas & Electric Co. as the operator. The facility utilizes batteries as its primary fuel source (MWH) and employs battery storage technology. It consists of one generator. The battery energy storage system (BESS) has a total storage capacity of 120 MWh, providing a duration of 4 hours. The battery chemistry is Lithium Ion (LIB).
The plant operates within the California Independent System Operator (CAISO) balancing authority and the Western Electricity Coordinating Council (WECC) NERC region. Escondido Energy Storage is ranked as the 171st largest power plant in California out of 300, and 652nd nationally out of 1205.
Generated from EIA, GEM, and public data sources
NERC Region
WECC
Balancing Authority
California Independent System Operator
Grid Voltage
12.5 kV
Regulatory Status
RE
Entity Type
Investor-Owned Utility
Sector
Electric Utility
−17 MWh
Net Charging
-142 MWh
Annual Net Energy
-0.1%
Capacity Factor
Positive values indicate net discharge (generation exceeds station load). Negative values indicate net charging. Pure battery storage plants are typically net negative due to round-trip efficiency losses.
No financial data available for this plant.
Point of Interconnection
Nearest Substation
Escondido Substation · 230 kV
Substation Distance
0.12 km
Operator
San Diego Gas & Electric
Coord Source
OSM spatial
Market Position
ISO/RTO Market
CAISO
LMP Node
BESSGEN_7_N001
Pricing Hub
TH_SP15_GEN-APND
Location Type
Pricing Node
Node Source
Curated node match
Mexico’s CFE plans 180MW solar-storage plant
CFE plans to build the Río Escondido solar-storage plant in Coahuila, with operations set to start in February 2028 and financing...
Renewable Energy Update 11.20.25
California added 1200 MW of battery energy storage to its electrical grid over the last six months, officials said.
A solar/battery project looks to offset hefty electric bills at wastewater facility
Officials predict the $3.2 million project in Escondido will pay for itself in about 20 years.
Escondido keeps battery storage ban while county drafts rules
The Escondido City Council on Oct. 1 extended its citywide moratorium on battery energy storage projects for a final time.
Last updated 2026-03-26
View all 10 articles