6.6 MW Solar operating in Middlesex, NJ — PJM Interconnection, LLC
6.6 MW
Nameplate Capacity
1
Generators
unit
Solar Photovoltaic
Technology
2016
Operating Since
Coordinates
40.4704, -74.3832
County
Middlesex, NJ
Nearby Plants
| Field | EIA | GEM | Wikidata |
|---|---|---|---|
| Operator | ILR Landfill | ILR Landfill | — |
| Owner(s) | ILR Landfill | — | — |
| Status | Operating | operating | — |
ILR Landfill is a 6.6 MW solar photovoltaic power plant located in Middlesex County, New Jersey. The plant began operating in 2016 and has one generator. It is owned and operated by ILR Landfill. The primary fuel source for the plant is solar energy. ILR Landfill is connected to the PJM Interconnection, LLC balancing authority and resides within the RFC NERC region.
In its most recent year of operation, ILR Landfill generated 9,630 MWh of electricity, achieving a capacity factor of 16.6%. The solar panels at the facility utilize a fixed tilt configuration. ILR Landfill is ranked as the 54th largest solar plant in New Jersey out of 328, and nationally it is ranked 2088 out of 7108. Financial data is available for this plant from LBNL.
Generated from EIA, GEM, and public data sources
NERC Region
RFC
Balancing Authority
PJM Interconnection, LLC
Grid Voltage
26 kV
Regulatory Status
RE
Entity Type
Investor-Owned Utility
Sector
Electric Utility
Nixon Lane Solar
350 MWh
Latest Month
9.6K MWh
Annual Generation
16.6%
Capacity Factor
$112.9/MWh
LCOE (Levelized Cost)
$28.2/MWh
Energy Value
Point of Interconnection
Nearest Substation
Sayreville Substation · 35 kV
Substation Distance
< 10 km
Operator
Jersey Central Power and Light
Coord Source
OSM spatial
Market Position
ISO/RTO Market
PJM
LMP Node
2156109753
Pricing Hub
WESTERN HUB
Node Source
EIA-860 direct report