1311.6 MW Nuclear operating in Lake, OH — PJM Interconnection, LLC
1,311.6 MW
Nameplate Capacity
1
Generators
unit
Nuclear
Technology
1987
Operating Since
Coordinates
41.8006, -81.1439
County
Lake, OH
Nearby Plants
Owner data does not fully agree across sources.
EIA typically reports the operating utility, while GEM resolves to the financial owner or parent corporation. Both can be correct.
| Field | EIA | GEM | Wikidata |
|---|---|---|---|
| Operator | Energy Harbor Nuclear Generation LLC | First Energy Nuclear Operating | FirstEnergy |
| Owner(s) | Energy Harbor Nuclear Generation LLC | Cleveland Electric Illuminating Co [100%] | — |
| Status | Operating | operating | — |
GEM identifies the owner as Cleveland Electric Illuminating Co [100%]
This entity is not yet in the GEM ownership database — chain unavailable.
The Perry Nuclear Power Plant is located on a 1,100 acres (450 ha) site on Lake Erie, 40 miles (64 km) northeast of Cleveland in North Perry, Ohio, US. The nuclear power plant is owned and operated by Vistra Corporation.
Read more on WikipediaThe Perry plant is a 1311.6 MW nuclear power plant located in Lake County, Ohio. It began operating in 1987 and is currently operated by Energy Harbor Nuclear Generation LLC. The plant utilizes a single nuclear generator. Perry is the largest of two nuclear plants in Ohio, and ranks 34th out of 55 nuclear plants nationally.
The plant operates within the PJM Interconnection, LLC balancing authority, which is part of the RFC NERC region. In the most recent year with available data, Perry generated 9,349,983 MWh of electricity, achieving a capacity factor of 81.4%.
Generated from EIA, GEM, and public data sources
NERC Region
RFC
Balancing Authority
PJM Interconnection, LLC
Grid Voltage
345 kV
Regulatory Status
NR
Entity Type
Independent Power Producer
Sector
IPP Non-CHP
950.4K MWh
Latest Month
9.3M MWh
Annual Generation
81.4%
Capacity Factor
No financial data available for this plant.
Market Position
ISO/RTO Market
PJM
LMP Node
PERRY_FE22 KV PR10
Pricing Hub
AEP-DAYTON HUB
Location Type
Generation Node
Node Source
Curated node match
Perry nuclear plant seeks to operate into 2060s, as Meta deal boosts output
PERRY TOWNSHIP, Ohio — Backed by a new long-term power agreement with Meta, the Perry Nuclear Power Plant is moving to extend its operating...
Meta advancing nuclear power for data centers across Ohio
Meta announced agreements with two energy companies to revive Ohio's two nuclear power plants, while using new advanced reactors to power...
Beaver Valley nuke plant will help power Meta in region. What to know
The agreement also includes two nuclear plants in Ohio.
The Meta-Vistra deal: A closer look
With last Friday's announcement regarding its vision for nuclear energy, Meta has entered into 20-year power purchase agreements (PPAs) for...
Last updated 2026-03-14
View all 10 articles