1.3 MW Solar operating in Atlantic, NJ — PJM Interconnection, LLC
1.3 MW
Nameplate Capacity
1
Generators
unit
Solar Photovoltaic
Technology
2012
Operating Since
Coordinates
39.4375, -74.6906
County
Atlantic, NJ
Nearby Plants
| Field | EIA | GEM | Wikidata |
|---|---|---|---|
| Operator | AES Distributed Energy | AES Distributed Energy | — |
| Owner(s) | AES Distributed Energy | — | — |
| Status | Operating | operating | — |
The AC Criminal Courts Complex SPE2, LLC is a 1.3 MW solar photovoltaic power plant located in Atlantic County, New Jersey. The plant began operating in 2012 and is owned and operated by AES Distributed Energy. It utilizes single-axis tracking technology to maximize solar energy capture. The plant is interconnected to the grid and operates within the PJM Interconnection, LLC balancing authority.
In its most recent year of operation, the plant generated 496 MWh of electricity, resulting in a capacity factor of 4.3%. According to state rankings, the AC Criminal Courts Complex SPE2, LLC is the 274th largest power plant in New Jersey out of 328 facilities. Nationally, it ranks as the 6072nd largest plant out of 7108. The plant's primary fuel source is solar energy.
Generated from EIA, GEM, and public data sources
NERC Region
RFC
Balancing Authority
PJM Interconnection, LLC
Grid Voltage
12.47 kV
Regulatory Status
NR
Entity Type
Independent Power Producer
Sector
Commercial Non-CHP
22 MWh
Latest Month
496 MWh
Annual Generation
4.3%
Capacity Factor
No financial data available for this plant.
Point of Interconnection
Nearest Substation
Cardiff Substation · 230 kV
Substation Distance
< 10 km
Operator
Atlantic City Electric
Coord Source
OSM spatial
Market Position
ISO/RTO Market
PJM
LMP Node
—
Pricing Hub
WESTERN HUB
Node Source
Shared substation inference
Substation identified. Node ID not yet resolved against ISO roster.