4 MW Solar operating in Cleveland, NC — Duke Energy Progress East
4 MW
Nameplate Capacity
1
Generators
unit
Solar Photovoltaic
Technology
2012
Operating Since
Coordinates
35.4681, -81.5099
County
Cleveland, NC
Nearby Plants
| Field | EIA | GEM | Wikidata |
|---|---|---|---|
| Operator | Palmetto Power Management LLC | Palmetto Power Management | — |
| Owner(s) | Kenwood Creek Holdings, LLC | Kenwood Creek Holdings LLC [100%] | — |
| Status | Operating | operating | — |
GEM identifies the owner as Kenwood Creek Holdings LLC [100%]
This entity is not yet in the GEM ownership database — chain unavailable.
Belwood Farm is a 4 MW solar photovoltaic power plant located in Cleveland County, North Carolina. The plant began operating in 2012 and has one generator. Palmetto Power Management LLC is the operator. The plant's primary fuel source is solar energy. Belwood Farm is ranked 578 out of 770 power plants in North Carolina, and 3534 out of 7108 plants nationally.
The plant operates within the Duke Energy Progress East balancing authority and the SERC NERC region. In its latest year of reported generation, Belwood Farm produced 6,004 MWh of electricity, achieving a capacity factor of 17.1%. The solar panels utilize a fixed tilt tracking system.
Generated from EIA, GEM, and public data sources
NERC Region
SERC
Balancing Authority
Duke Energy Progress East
Grid Voltage
12.47 kV
Regulatory Status
NR
Entity Type
Independent Power Producer
Sector
IPP Non-CHP
406 MWh
Latest Month
6.0K MWh
Annual Generation
17.1%
Capacity Factor
No financial data available for this plant.
This plant is outside organized wholesale electricity markets (ISOs/RTOs). Nodal pricing data is not available.