3.5 MW Solar operating in Tulare, CA — California Independent System Operator
3.5 MW
Nameplate Capacity
3
Generators
units
Solar Photovoltaic
Technology
2014
Operating Since
Coordinates
36.2660, -119.1284
County
Tulare, CA
Nearby Plants
| Field | EIA | GEM | Wikidata |
|---|---|---|---|
| Operator | Altus Power America Management, LLC | Altus Power America Management | — |
| Owner(s) | Altus Power America Management, LLC | — | — |
| Status | Operating | operating | — |
Exeter Solar is a 3.5 MW solar photovoltaic power plant located in Tulare County, California. The plant began operating in 2014 and consists of 3 generators utilizing fixed tilt solar tracking. Altus Power America Management, LLC is the plant's operator, and the facility interconnects to the California Independent System Operator (CAISO) balancing authority within the Western Electricity Coordinating Council (WECC) NERC region.
In its latest year of reported generation, Exeter Solar produced 4,578 MWh of electricity, achieving a capacity factor of 14.9%. The plant is ranked as the 361st largest solar facility in California out of 862, and 3663rd nationally out of 7108. The plant's primary fuel source is solar energy (SUN).
Generated from EIA, GEM, and public data sources
NERC Region
WECC
Balancing Authority
California Independent System Operator
Grid Voltage
12.47 kV
Regulatory Status
NR
Entity Type
Independent Power Producer
Sector
IPP Non-CHP
274 MWh
Latest Month
4.6K MWh
Annual Generation
14.9%
Capacity Factor
No financial data available for this plant.
Point of Interconnection
Nearest Substation
Venida Substation · 66 kV
Substation Distance
< 10 km
Operator
Southern California Edison
Coord Source
OSM spatial
Market Position
ISO/RTO Market
CAISO
LMP Node
—
Pricing Hub
TH_ZP26_GEN-APND
Node Source
OSM spatial match
Substation identified. Node ID not yet resolved against ISO roster.