173 MW Natural Gas operating in Hardin, TX — Midcontinent Independent Transmission System Operator, Inc..
173 MW
Nameplate Capacity
2
Generators
units
Natural Gas Fired Combustion Turbine
Technology
2001
Operating Since
Coordinates
30.3038, -94.2526
County
Hardin, TX
Nearby Plants
| Field | EIA | GEM | Wikidata |
|---|---|---|---|
| Operator | Entergy Texas Inc. | Entergy Texas | — |
| Owner(s) | Entergy Texas Inc. | Entergy | — |
| Status | Operating | — | — |
The Hardin County Peaking Facility is a 173 MW natural gas-fired power plant located in Hardin County, Texas. The plant began operating in 2001 and consists of two natural gas-fired combustion turbine generators. It is owned by Entergy and operated by Entergy Texas Inc. The plant's installed cost was $458 per kW, according to FERC data.
The Hardin County Peaking Facility operates within the Midcontinent Independent Transmission System Operator (MISO) balancing authority and the SERC NERC region. In the most recent year of data, the plant generated 194,646 MWh of electricity, achieving a capacity factor of 12.8%. The plant ranks 126th out of 144 power plants in Texas and 784th out of 945 plants nationally.
Generated from EIA, GEM, and public data sources
NERC Region
SERC
Balancing Authority
Midcontinent Independent Transmission System Operator, Inc..
Grid Voltage
230 kV
Regulatory Status
RE
Entity Type
Investor-Owned Utility
Sector
Electric Utility
3.7K MWh
Latest Month
194.6K MWh
Annual Generation
12.8%
Capacity Factor
$448/kW
Installed Cost
$41.7/MWh
Operating Cost
Entergy Texas, Inc.
Reporting Utility
Annual Capital & Operating Expenses
Cumulative Installed Cost
Per-Unit Cost Trends
Market Position
ISO/RTO Market
MISO
LMP Node
ESS.CYPRESS1CT
Pricing Hub
TEXAS.HUB
Node Source
EIA-860 direct report
Entergy Texas reaches settlement on Bright Future rate proposal
Entergy Texas has reached a settlement agreement with the Public Utility Commission staff and the intervening parties in its base rate case filed in July 2022.
Entergy Texas files proposal to ensure a bright future for Southeast Texas
The company filed a rate proposal with the Public Utility Commission of Texas to ensure it can provide reliable, affordable and sustainable...
Last updated 2026-03-14