10.5 MW Wind operating in Twin Falls, ID — Idaho Power Company
10.5 MW
Nameplate Capacity
1
Generators
unit
Onshore Wind Turbine
Technology
2011
Operating Since
Coordinates
42.7917, -114.9998
County
Twin Falls, ID
Nearby Plants
Owner data does not fully agree across sources.
EIA typically reports the operating utility, while GEM resolves to the financial owner or parent corporation. Both can be correct.
| Field | EIA | GEM | Wikidata |
|---|---|---|---|
| Operator | Idaho Wind Partners 1 LLC | Idaho Wind Partners | — |
| Owner(s) | Idaho Wind Partners 1 LLC | Idaho Wind Partners [100%] | — |
| Status | Operating | operating | — |
GEM identifies the owner as Idaho Wind Partners [100%]
This entity is not yet in the GEM ownership database — chain unavailable.
Pilgrim Stage Wind Park is a 10.5 MW wind power plant located in Twin Falls County, Idaho. The facility began operating in 2011 and is owned and operated by Idaho Wind Partners 1 LLC. The plant utilizes a single onshore wind turbine manufactured by GE Wind, model GE1.5-82.5. Key engineering specifications include a hub height of 80 meters and a rotor diameter of 82.5 meters.
The plant's latest annual generation was 34,265 MWh, achieving a capacity factor of 37.2%. Pilgrim Stage Wind Park operates within the Idaho Power Company balancing authority and the Western Electricity Coordinating Council (WECC) NERC region. The plant ranks 31st out of 34 wind facilities in Idaho and 1134th nationally out of 1424 wind plants.
Generated from EIA, GEM, and public data sources
NERC Region
WECC
Balancing Authority
Idaho Power Company
Grid Voltage
34.5 kV
Regulatory Status
NR
Entity Type
Independent Power Producer
Sector
IPP Non-CHP
2.8K MWh
Latest Month
34.3K MWh
Annual Generation
37.2%
Capacity Factor
No financial data available for this plant.
This plant is outside organized wholesale electricity markets (ISOs/RTOs). Nodal pricing data is not available.