159.5 MW Natural Gas operating in Valencia, NM — Public Service Company of New Mexico
159.5 MW
Nameplate Capacity
1
Generators
unit
Natural Gas Fired Combustion Turbine
Technology
2008
Operating Since
Coordinates
34.6110, -106.7319
County
Valencia, NM
Nearby Plants
| Field | EIA | GEM | Wikidata |
|---|---|---|---|
| Operator | Valencia Power LLC | Valencia Power | — |
| Owner(s) | Valencia Power LLC | Onward Energy Holdings | — |
| Status | Operating | — | — |
The Valencia Energy Facility is a 159.5 MW natural gas-fired power plant located in Valencia County, New Mexico. The plant began operating in 2008 and is owned by Onward Energy Holdings, with Valencia Power LLC as the operator. It consists of a single natural gas-fired combustion turbine generator. The facility ranks as the 9th largest power plant in New Mexico out of 11 total plants, and 811th nationally out of 945 plants.
In the most recent year with available data, the Valencia Energy Facility generated 76,829 MWh of electricity, resulting in a capacity factor of 5.5%. The plant operates within the Western Electricity Coordinating Council (WECC) NERC region and is under the balancing authority of the Public Service Company of New Mexico.
Generated from EIA, GEM, and public data sources
NERC Region
WECC
Balancing Authority
Public Service Company of New Mexico
Grid Voltage
115 kV
Regulatory Status
NR
Entity Type
Independent Power Producer
Sector
IPP Non-CHP
6.8K MWh
Latest Month
76.8K MWh
Annual Generation
5.5%
Capacity Factor
No financial data available for this plant.
This plant is outside organized wholesale electricity markets (ISOs/RTOs). Nodal pricing data is not available.
16 groups call on NM governor for more transparency, public input on Project Jupiter data center
Sixteen environmental and community groups called on Gov. Michelle Lujan Grisham for more transparency in the Project Jupiter development.
Los Lunas, Pacific Fusion celebrate opening manufacturing hub
LOS LUNAS — The village of Los Lunas marked a milestone in its economic development strategy with the ribbon-cutting ceremony for Pacific...
THURS: BernCo Planning Commission approves substation permit in Northeast Heights amid public outcry, + More
The project proposes the installation of a new utility structure, estimated to cost around $35 million, in the city's Northeast Heights area...
Pacific Fusion to invest in build center in Los Lunas
221 S. Main St., Suite B Belen, NM 87002. Phone: 505-864-4472. Email: vcnb@news-bulletin.com · news-bulletin.com...
Last updated 2026-03-14
View all 10 articles