14.6 MW Muni. Waste operating in New London, CT — ISO New England Inc.
14.6 MW
Nameplate Capacity
1
Generators
unit
Municipal Solid Waste
Technology
1995
Operating Since
Coordinates
41.5844, -72.0413
County
New London, CT
Nearby Plants
| Field | EIA | GEM | Wikidata |
|---|---|---|---|
| Operator | Wheelabrator Environmental Systems | Wheelabrator Environmental Systems Inc | — |
| Owner(s) | Eastern Conn Res Recvy Auth | Wheelabrator Technologies Holdings | WIN Waste Innovations |
| Status | Operating | operating | — |
Wheelabrator Lisbon is a 14.6 MW waste-to-energy power plant located in New London County, Connecticut. The plant, which began operating in 1995, utilizes municipal solid waste (MSW) as its primary fuel source. It has one generator and is owned by Wheelabrator Technologies Holdings, with Wheelabrator Environmental Systems as the operator. The plant is connected to the ISO New England Inc. balancing authority and operates within the NPCC NERC region.
In the most recent year of data, Wheelabrator Lisbon generated 99,768 MWh of electricity, achieving a capacity factor of 78.0%. The facility ranks as the 4th largest of 4 MSW plants in Connecticut, and 45th out of 56 nationally.
Generated from EIA, GEM, and public data sources
NERC Region
NPCC
Balancing Authority
ISO New England Inc.
Grid Voltage
115 kV
Regulatory Status
NR
Entity Type
Commercial
Sector
IPP Non-CHP
7.8K MWh
Latest Month
99.8K MWh
Annual Generation
78.0%
Capacity Factor
No financial data available for this plant.
Point of Interconnection
Nearest Substation
Lisbon Substation · 115 kV
Substation Distance
0.043 km
Operator
Wheelabrator Technologies Inc.
Coord Source
OSM spatial
Market Position
ISO/RTO Market
ISO-NE
LMP Node
UN.LISBON 115 LISB
Pricing Hub
.Z.CONNECTICUT
Node Source
Curated node match
Environmental groups urge closing of state’s only ash landfill, call it an unnecessary waste solution
The state's only landfill for the ash produced by waste-to-energy plants wants to...
CT landfill expansion plan faces opposition
The Wheelabrator Putnam ash landfill gets another public hearing in mid-October, as it rolls closer to an expansion that will double the...
Middletown locks in price for 10-year waste disposal contract
MIDDLETOWN — Led by its Solid Waste Negotiating Committee, the Eastern Connecticut Resource Recovery Authority and Wheelabrator have...
Fire damages trash plant in Bridgeport
One of the three boilers in the Wheelabrator trash-to-energy plant was damaged in a two-alarm fire on Tuesday night that remained under investigation Wednesday.
Last updated 2026-03-14