2 MW Hydro operating in Alpena, MI — Midcontinent Independent Transmission System Operator, Inc..
2 MW
Nameplate Capacity
4
Generators
units
Conventional Hydroelectric
Technology
1990
Operating Since
Coordinates
45.0934, -83.5022
County
Alpena, MI
Nearby Plants
| Field | EIA | GEM | Wikidata |
|---|---|---|---|
| Operator | Eagle Creek Renewable Energy, LLC | — | — |
| Owner(s) | Thunder Bay Power Co LLC | — | — |
| Status | Operating | — | — |
The Four Mile Hydropower Project is a 2 MW hydroelectric power plant located in Alpena County, Michigan. The plant began operating in 1990 and is owned and operated by Eagle Creek Renewable Energy, LLC. It utilizes conventional hydroelectric technology and consists of four generators.
The plant's primary fuel source is water (WAT). In its latest year of reported generation, the facility produced 8,957 MWh of electricity, achieving a capacity factor of 51.1%. The Four Mile Hydropower Project operates within the Midcontinent Independent Transmission System Operator, Inc. (MISO) balancing authority and the ReliabilityFirst Corporation (RFC) NERC region. It is ranked as the 37th largest power plant out of 50 in Michigan, and 1210th out of 1464 nationally.
Generated from EIA, GEM, and public data sources
NERC Region
RFC
Balancing Authority
Midcontinent Independent Transmission System Operator, Inc..
Grid Voltage
34.5 kV
Regulatory Status
NR
Entity Type
Independent Power Producer
Sector
IPP Non-CHP
763 MWh
Latest Month
9.0K MWh
Annual Generation
51.1%
Capacity Factor
No financial data available for this plant.
Point of Interconnection
Nearest Substation
Four Mile Substation · 138 kV
Substation Distance
0.106 km
Operator
Alpena Power Company
Coord Source
OSM spatial
Market Position
ISO/RTO Market
MISO
LMP Node
CONS.ALPENA
Pricing Hub
MICHIGAN.HUB
Location Type
Load Zone
Node Source
Curated node match