71.5 MW Distillate Oil operating in Suffolk, NY — New York Independent System Operator
71.5 MW
Nameplate Capacity
2
Generators
units
Petroleum Liquids
Technology
1966
Operating Since
Coordinates
40.9599, -72.8655
County
Suffolk, NY
Nearby Plants
| Field | EIA | GEM | Wikidata |
|---|---|---|---|
| Operator | National Grid Generation LLC | National Grid Generation | — |
| Owner(s) | National Grid Generation LLC | National Grid | — |
| Status | Operating | — | — |
Shoreham is a 71.5 MW petroleum liquid-fueled power plant located in Suffolk County, New York. The plant began operating in 1966 and consists of two generators utilizing petroleum liquids technology. It is owned by National Grid, a company based in the United Kingdom, and operated by National Grid Generation LLC. Shoreham operates within the New York Independent System Operator (NYISO) balancing authority and the Northeast Power Coordinating Council (NPCC) NERC region.
In the most recent year with available data, Shoreham generated 353 MWh of electricity, resulting in a capacity factor of 0.1%. The plant's installed cost was $487.65 per kW, according to FERC data. Shoreham is ranked 4th out of 66 similar plants in New York state, and 78th out of 886 plants nationally.
Generated from EIA, GEM, and public data sources
NERC Region
NPCC
Balancing Authority
New York Independent System Operator
Grid Voltage
138 kV
Regulatory Status
RE
Entity Type
Investor-Owned Utility
Sector
Electric Utility
99 MWh
Latest Month
353 MWh
Annual Generation
0.1%
Capacity Factor
$144/kW
Installed Cost
$1079.2/MWh
Operating Cost
National Grid Generation LLC
Reporting Utility
Annual Capital & Operating Expenses
Cumulative Installed Cost
Per-Unit Cost Trends
Point of Interconnection
Nearest Substation
SHOREHAM_IC_1
Substation Distance
< 10 km
Coord Source
NYISO direct
Market Position
ISO/RTO Market
NYISO
LMP Node
23715
Pricing Hub
NYISO Zone K
Node Source
EIA-860 direct report
Cuba Begins Testing First Battery Energy Storage System to Boost Grid Stability
As part of the country’s strategic program to strengthen the stability of the national grid, Cuba has begun load testing of the first unit of a battery energy storage system (BESS) at the El Cotorro substation in Havana. This is the first of four systems with a total capacity of 200 MW. According...
Shoreham battery storage lawsuit dismissed by state judge
A state judge dismissed the Shoreham-Wading River School District's lawsuit over payments from a battery storage facility developer,...
Opinion | Hochul’s nuclear plant announcement draws sharp criticism from nuclear energy opponents
Governor Kathy Hochul continued her push for nuclear power in New York State with her June 21 announcement that she has directed the New...
5 People Cut Fence, Illegally Entered Shoreham Nuclear Power Plant: PD
SHOREHAM, NY — Suffolk County Crime Stoppers and Suffolk County Police Seventh Squad detectives are asking for the public's help to identify...
Last updated 2026-03-25